Owner: Merit R., two-storey house in Haabneeme. Location: near Põhkkonna steps, Haabneeme, Viimsi parish. Job number: 1745.
Site visit. The surveyor checked the location of the outlet and the ventilation duct, and the frame installation, partition and tiling had their own days in the 5 business day schedule.
Dismantling of the old device and installation of the new one. On the first day, the old floor toilet was removed on the company's trailer, and on the second day, the wall-hung toilet frame was attached directly to the wooden posts of the floor and wall, because the plasterboard cannot support a 400-kilogram load.
Pressure test and partition. The water pipes remained under pressure overnight, the paper placed under the frame was dry in the morning, the fixing points of the frame were checked with a spirit level, and the partition covering the frame was tiled in 2 days.
Ten consecutive flushes. On the fifth day, the toilet was hung with a 3-liter and 6-liter two-stage flush, the windowless toilet was replaced with a 100 mm ducted non-return valve fan that moves 90 cubic metres of air per hour, and the flush was tested ten times in a row.
Repair price: €2,104.80 including VAT: WC complete renovation 1 × €1,900 = €1,900, fan replacement with non-return valve 1 × €145 = €145 and Viimsi repair day travel costs for 5 days × €11.96 = €59.80.
Repair duration: 5 working days in 2025, including demolition 1 day, frame and pipes 1 day, bulkhead and tiling 2 days, and toilet and fan 1 day.
Finished room: The frame of the wall-mounted toilet supports 400 kilograms, and the paper under it remained dry overnight with pressurized pipes.